This is an unrestriccted procurement. The work consists of furnishing all plant, labor, materials and equipment, repairing two (2) existing dikes and extending two (2) existing dikes at Warfield Pt Dike 1L and Island 84 Dike 2U, in Chicot County, Arkansas. Principal features of the work include mobilization and demobilization; furnishing, delivering and placing Graded Stone "A".

This work will be performed in the Mississippi River and varying water depths and currents may be encountered. Currents usually encountered at the sites of the work during low water period may vary from about one mile per hour to about six miles per hour.

Construction of the dikes may require both floating plant and land based equipment. The work shall be completed as expeditiously as possible even though river conditions may become increasingly severe as construction progresses. The work requires steady and uninterrupted progress to minimize loss of stone during construction.

The value of the proposed work is between $1,000,000.00 and $5,000,000.00.

Plans and specifications will be available on the Federal Business Opportunities (FBO) Web Page at http://www.fedbizopps.gov/. Bidders may register on the Interested Vendor's List (IVL) at http://www.fbo.gov/ and retrieve an IVL from the same location. Compact disc and hardcopies will not be available. Bidders should check often for changes (AMENDMENTS). Issue date on or around July 13, 2018. Bid opening date on or around August 14, 2018.

Attachments

Dates

Deadline: Tuesday, August 14, 2018

Date Published: Friday, July 13, 2018

Date Updated: Friday, July 13, 2018

Contact

Jason M. Carlock

jason.m.carlock@usace.army.mil

Attn: CEMVK-CT, 4155 Clay Street, Vicksburg, Mississippi 39183-3435

(601) 631-5793

Save 40% on business checks